Recent aerial surveying of one of Hanford’s largest waste sites cost an estimated $700,000 less than traditional ground surveying methods, reduced worker risk, and took days instead of months to complete.
Construction work continues at Hanford's Waste Treatment Plant, which has reached 77 feet high in places. Read more in today's Tri-City Herald.
Recovery Act job creation figures for the Hanford Site that are posted on recovery.gov and
www.hanford.gov/recovery are different. They are counting different things. This backgrounder explains the different ways jobs creation is being tracked and reported.
The Pretreatment (PT) Facility at the Hanford Waste Treatment and Immobilization Plant (Vit Plant) now reaches an impressive 77 feet in places and continues to rise steadily as concrete and steel are installed.